The process waste generated at the Britannia and Lemieux Island Water Purification Plants (WPPs) originates from both the settling and filter backwashing processes. Since the plants were built, these process wastes from the plants, comprised of settled and filtered particulate materials, have been discharged back to the Ottawa River. Following provincial orders to discontinue this practice, the City of Ottawa completed a study in October 2002 that followed the Municipal Class Environmental Assessment (Class EA) process for a Schedule B project, to select a management practice to divert these materials from the river.
The selected alternative consisted of discharging the process sludges to the City’s sanitary collection system for treatment at ROPEC. The project is currently in the design phase and construction is scheduled to begin in this spring.
Open House on Thursday February 105-8 pm at the Filter Gallery at Lemieux Island Water Purification Plant
This open house will present information on the implementation process and overall design elements of the waste management project. CH2M HILL has been retained to assist the City of Ottawa with the engineering design for this project.
For more information and/or to submit comments, please contact:
M. Ted Woytowich, P.Eng.
Senior Project Manager
100 Constellation Cres.
6th floor
Nepean ON K2G 6J8
Phone : 613-580-2424 Ext. 22721
Fax : 613-560-6064
E-mail : Theodore.Woytowich@ottawa.ca
Norm Newman, P.Eng
Senior Project Engineer
CH2M HILL
1101 Prince of Wales Drive, Suite 330
Ottawa ON K2C 3W7
Phone : 613-723-8700, Ext. 224
Fax : 613-723-7489
E-mail : norm.newman@ch2m.com